gantt_textex1.php
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
<?php // content="text/plain; charset=utf-8"
require_once ("jpgraph/jpgraph.php");
require_once ("jpgraph/jpgraph_gantt.php");
require_once ("jpgraph/jpgraph_flags.php");
 
$graph = new GanttGraph(0,0);
$graph->SetBox();
$graph->SetShadow();
 
// Add title and subtitle
$graph->title->Set("Example with added texts");
$graph->title->SetFont(FF_ARIAL,FS_BOLD,12);
 
// Show day, week and month scale
$graph->ShowHeaders(GANTT_HDAY | GANTT_HWEEK | GANTT_HMONTH);
 
// Set table title
$graph->scale->tableTitle->Set("(Rev: 1.22)");
$graph->scale->tableTitle->SetFont(FF_FONT1,FS_BOLD);
$graph->scale->SetTableTitleBackground("silver");
 
// Modify the appearance of the dividing lines
$graph->scale->divider->SetWeight(3);
$graph->scale->divider->SetColor("navy");
$graph->scale->dividerh->SetWeight(3);
$graph->scale->dividerh->SetColor("navy");
 
// Use the short name of the month together with a 2 digit year
// on the month scale
$graph->scale->month->SetStyle(MONTHSTYLE_SHORTNAMEYEAR2);
$graph->scale->month->SetFontColor("white");
$graph->scale->month->SetBackgroundColor("blue");
 
// 0 % vertical label margin
$graph->SetLabelVMarginFactor(1);
 
// Format the bar for the first activity
// ($row,$title,$startdate,$enddate)
$activity = new GanttBar(0,"Project","2001-12-21","2002-01-07","[50%]");
 
// Yellow diagonal line pattern on a red background
$activity->SetPattern(BAND_RDIAG,"yellow");
$activity->SetFillColor("red");
 
// Set absolute height
$activity->SetHeight(10);
 
// Specify progress to 60%
$activity->progress->Set(0.6);
$activity->progress->SetPattern(BAND_HVCROSS,"blue");
 
// Format the bar for the second activity
// ($row,$title,$startdate,$enddate)
$activity2 = new GanttBar(1,"Project","2001-12-21","2001-12-27","[30%]");
 
// Yellow diagonal line pattern on a red background
$activity2->SetPattern(BAND_RDIAG,"yellow");
$activity2->SetFillColor("red");
 
// Set absolute height
$activity2->SetHeight(10);
 
// Specify progress to 30%
$activity2->progress->Set(0.3);
$activity2->progress->SetPattern(BAND_HVCROSS,"blue");
 
// Finally add the bar to the graph
$graph->Add($activity);
$graph->Add($activity2);
 
// Add text to top left corner of graph
$txt1 = new Text();
$txt1->SetPos(5,2);
$txt1->Set("Note:\nEstimate done w148");
$txt1->SetFont(FF_ARIAL,FS_BOLD,12);
$txt1->SetColor('darkred');
$graph->Add($txt1);
 
// Add text to the top bar
$txt2 = new Text();
$txt2->SetScalePos("2002-01-01",1);
$txt2->SetFont(FF_ARIAL,FS_BOLD,12);
$txt2->SetAlign('left','center');
$txt2->Set("Remember this!");
$txt2->SetBox('yellow');
$graph->Add($txt2);
 
 
// Add a vertical line
$vline = new GanttVLine("2001-12-24","Phase 1");
$vline->SetDayOffset(0.5);
//$graph->Add($vline);
 
// ... and display it
$graph->Stroke();
?>